Using Equipment Manager to configure the AWMA iRiser

Observant Support

Created: ; updated: .

This article covers the steps needed to configure the Linak actuator that operates an iRiser.

Correct configuration will ensure the iRiser always operates as expected:

  • the iRiser closes fully, putting pressure on the seal and completely shutting off water flow
  • if iRiser operation is interrupted, an appropriate warning is raised
  • minimises the chance of "false alarm" warnings

Configuration

  1. The Linak actuator can only be configured after the iRiser is installed and has been fully closed.

  2. With the iRiser closed, log into Global and visit Manage Equipment. Select the required site and iRiser, and make a note of its reported Actual Position:
    000529.png

  3. Select Settings and set these values:
    1. Operating profile: iRiser
    2. Out Stop: 5mm more than the Actual Position noted in the last step. In this example, we would set it to 247 mm
    3. Tolerance: 10 mm
    4. Position meaning: In Is Open
  4. Check that the settings are correct, then click Update.

 

 